Update on the Development of 35th Street between Park and Madison Avenue

MHNA officers and building adjacent Co-op president met recently with Bruce Eichner, CEO at Continuum Company to express community concerns and confirm details of the new building development on 35th St. between Park and Madison Avenue.

Mr. Eichner is a former resident of Murray Hill, community investment-minded and professional.

-$90 million project
Architects: SLCE Architects
Interior Design: INC

Sidewalk sheds have gone up around the Community Church property on 35th Street between Madison and Park Avenue, and demolition has begun on several of the historic townhouses. 

Here is what we learned:
Work hours are 7AM to 6PM. Work may take place at other times only if the site has a construction variance from the City.

REPORT offenses direct to 311.

Demolition is expected to last at least 60 days.
Brick by brick removal of the actual Church building where in contact with side of 16 Park Avenue

THE BUILDING:
-Construction will begin early 2025 through 2026
-Occupancy early 2027
-16 stories, 170 feet tall (additional 1 1/2 stories at rear of building to house mechanicals,
elevator)
-Some light sandstone material will blend with streetscape
-15 ft. step back at the 13th to 16th floor
-137 Luxury Condominiums, 1,200 sq ft, Approx cost: $3million each
-Terraces north side (35th) of building
-Ground Floor Professional spaces
-Garage, underground for tenants only under west side of building (Madison Avenue)
-30m foot wide ground floor terrace as an amenity for the residents of the building

We will continue to monitor the premises and activity and provide timely information. We will
have a point person to contact for questions or problem situations.

We hope everyone will be understanding during this major upheaval in our special historic community.