The New York City Department of Design and Construction (NYCDDC) continues to manage the capital construction Infrastructure Upgrade Project #MED607. Work includes, but is not limited to, the installation of catch basins at various locations, utility upgrades, limited sewer upgrades, new hydrant installation and the installation of new water main pipes in various locations. This project has an anticipated completion date of Winter 2025.
Work Completed: Fourth Quarter 2024
Relocation of 12” watermain on 1st Avenue between East 35th Street and East 36th Street.
Proposed Work Schedule: First Quarter 2025 Work continues for the 36 inch trunk water main installation on E. 35th St. btw. 2nd and 3rd Avenues. The city contractor will continue utility work along East 35th St. btw. 2nd Ave and QMT Exit.
(Weekends only-8:00am-4:30pm). The city contractor will continue supporting Con Edison utility relocation work along the east side of 1st Ave btw. E. 34th St. and E. 36th St. City contractor will install 36’ Trunk Watermain and backfill open trenches at E. 35th St. btw. 3rd Ave & QMT Exit. The city contractor will perform trench excavation along south side of E. 35th St. btw. QMT Exit & 2nd Ave.
Community Impacts
During construction hours, you can expect increased levels of dust, noise, and heavy equipment. In addition, vehicular lane closures or detours may occur. There may be limited curbside parking and you will be notified if certain bus stops will be moved. Please note, signs are posted where necessary and emergency vehicle/pedestrian/building access will be maintained at-all-times.
Community Construction Liaison (CCL)
The DDC has assigned Youseph Rasheed, as the Community Construction Liaison (CCL) for this project. Contact Youseph for your project related inquiries/concerns.
Phone: 646-768-9105
Email: 2ndAvenue.ccl@gmail.com
Field Office: 300 E. 40th St., NY, NY 10016
Office Hours: Mon-Fri 7:00am-3:30pm
DDC Video:
https://www1.nyc.gov/site/ddc/projects/videos. page
Newsletter Distribution
Distribution of Construction Newsletters for this project are within the footprint of the project & Manhattan’s Community Board #6.
Accommodations for Individuals with Disabilities If you or someone you know may be uniquely impacted by this project, please contact the project CCL and/or Resident Engineer, as soon as possible, to make them aware of your situation or concern.